Calendar Days Vs Working Days - The samples in the below picture show the same 25 calendar days interval yet they produce different working days (18 to 20 days) considering how many of the weekend days will fall into the given 25 days period. Is there a column that can be selected to show calendar days? Duration are entered in as working time and sometimes you want to see the actual days. They mean 14 calendar days (according to the instructions), but if i put fs+14d, or fs+2w, then project is interpreting that to mean 14 working days. By the way, i tried switching to a 7 day week calendar, but that didn't work. That means all days are going to be working days. In order to know how many working days we need a starting date as a reference.

Is there a column that can be selected to show calendar days? 365 day activity is coming up as 150+ days and 12 mo is coming up as 340+ days. Hi planners is it possible to have variance target1 early finish in calendar days instead of working days ? I need it to plan using 14 calendar days.

4) if you use calendar days and not working days, it becomes more difficult to get meaningful reports on resource utilisation & forecasts (brian, you only booked 4hrs against my project last. Hi, i'm using project 2010 and i have a project that is created and planned using working days. You could make a 7 days/week calendar and make that calendar the project calendar, which means that every task will get it by default. I just want to show the number of days delayed. Duration are entered in as working time and sometimes you want to see the actual days. The samples in the below picture show the same 25 calendar days interval yet they produce different working days (18 to 20 days) considering how many of the weekend days will fall into the given 25 days period.

I just want to show the number of days delayed. The contract i'm working on requires a project schedule showing the duration in calendar days. They mean 14 calendar days (according to the instructions), but if i put fs+14d, or fs+2w, then project is interpreting that to mean 14 working days. You could make a 7 days/week calendar and make that calendar the project calendar, which means that every task will get it by default. Is there a column that can be selected to show calendar days?

If i entered 8d in the duration, it will count as 10 calendar days instead (or sometimes even 12 days, depending on whether the task starts on a friday, and. 365 day activity is coming up as 150+ days and 12 mo is coming up as 340+ days. They mean 14 calendar days (according to the instructions), but if i put fs+14d, or fs+2w, then project is interpreting that to mean 14 working days. Currently i've tried to schedule a task that ends on a saturday and if auto shortens it to friday.

4) If You Use Calendar Days And Not Working Days, It Becomes More Difficult To Get Meaningful Reports On Resource Utilisation & Forecasts (Brian, You Only Booked 4Hrs Against My Project Last.

However, i do have a few task, such as like let material set for 8 days, that are dependent on calendar days. Currently i've tried to schedule a task that ends on a saturday and if auto shortens it to friday. I just want to show the number of days delayed. Hi, i'm using project 2010 and i have a project that is created and planned using working days.

In The Past I Used A Formula That Someone On One Of These Forums Shared With Me, But Then I Changed Employers And Lost That Formula.

In order to know how many working days we need a starting date as a reference. For example, customer says we must hold a kickoff within 2 weeks of contract award. By the way, i tried switching to a 7 day week calendar, but that didn't work. Is there a way to change the format of the calendar from work days to calendar days?

Is There A Column That Can Be Selected To Show Calendar Days?

Thanks in advance for your input. You could make a 7 days/week calendar and make that calendar the project calendar, which means that every task will get it by default. The contract i'm working on requires a project schedule showing the duration in calendar days. If you use calendar days and not working days, you would need to alter your lags/durations to project an accurate date, each time the project slipped.

I Need It To Plan Using 14 Calendar Days.

That means all days are going to be working days. If i entered 8d in the duration, it will count as 10 calendar days instead (or sometimes even 12 days, depending on whether the task starts on a friday, and. If you put in a month with a calendar that has 5 day work weeks and holidays. 365 day activity is coming up as 150+ days and 12 mo is coming up as 340+ days.

Duration are entered in as working time and sometimes you want to see the actual days. Is there a column that can be selected to show calendar days? However, i do have a few task, such as like let material set for 8 days, that are dependent on calendar days. If you use calendar days and not working days, you would need to alter your lags/durations to project an accurate date, each time the project slipped. Currently i've tried to schedule a task that ends on a saturday and if auto shortens it to friday.